29th September 2018.

The 2 photo's above show the work completed.

The Blue lines indicate the track before.

Its 8:30 on Saturday morning. The line that leads to the central wales line to the right is being lifted and loaded on the rake of wagons. The are just past the huge crane is being readied for the new points that can be seen stored on the left platform.

The Northbound line is now being removed.

The new pre-prepared point work is transported down and rested on the platform.

The redundant signal gantry and points are removed. Trains for the central wales line are now going to be signalled from Cardiff !

The weekend work brought a large number of Locomotives to the area. Nice to see them close up and stationary.